EPA and Emergency and Rapid Response Services (ERRS) contractors and Superfund Technical Assessment and Response Team (START) contractors mobilized to the Site on Monday, June 2nd.
Activities completed from 06/02/2025 to 06/04/2025 include the following:
- ERRS received and staged equipment and supplies (including an excavator and skid steer) needed for completion of removal activities.
- START completed background air monitoring and sampling before any demolition work began at four locations along the site perimeter.
- ERRS personnel began and maintained use of the fire hydrant to wet the debris for dust control.
- ERRS demolished the on-site structures and began stockpile material for future loadout and transportation/disposal.
- START conducted daily air sampling for asbestos and air monitoring for particulates at four locations along the site perimeter during the removal.
- Loadout of debris began on Wednesday, June 4th. An estimated total 105 cubic yards has been hauled off-site as of 06/04/2025.
Planned activities from 06/05/2025 to 06/07/2025 include the following:
- ERRS will continue to load debris to for off site disposal. Remaining amount estimated to be < 45% of original pile.
- START will continue to run air monitoring stations and conduct asbestos air sampling along perimeter of site activities outside of the exclusion zone.
- ERRS will conduct a soil scrape within the exclusion zone.