U.S. flag

An official website of the United States government

Dot gov

Official websites use .gov
A .gov website belongs to an official government organization in the United States.

HTTPS

Secure .gov websites use HTTPS
A lock () or https:// means you’ve safely connected to the .gov website. Share sensitive information only on official, secure websites.

Flat Rock Creek Drums

 
Site Contact:
Jennifer Polk
On Scene Coordinator

(polk.jennifer@epa.gov)

Site Location:
4223 N MLK Jr Blvd
Tulsa, OK 74106
response.epa.gov/flatrockcreekdrums
NRC#: 1411880

On September 25, 2024, the EPA received notification from the National Response Center regarding abandoned 55-gallon steel drums near Flat Rock Creek in Tulsa, Oklahoma. EPA conducted a Removal Site Evaluation (RSE) of three dump locations at 4223 Martin Luther King, Jr. Blvd. in Tulsa, OK, from September 28, 2024, to October 25, 2024.  During the RSE, EPA conducted an inventory of 103 of the 109 drums and performed Hazard Categorization (HAZCAT) of the substances in the drums. Six of the drums were empty and not analyzed. Any leaking drums were placed into overpacks and relocated into secondary containment. The drums were then covered and contained with poly and tarps to prevent rainwater, and orange construction fencing and caution tape was placed around the dump areas and secondary containment to warn off passersby.  EPA continued to visit the site at least two times a week to maintain secondary containment, with more frequent visits occurring during inclement weather.

From the HAZCAT results, EPA determined that of the 103 drums, 42 contained substances that were non-hazardous. The contents of 61 drums exhibited characteristics of hazardous substances. 

On April 29, 2025, EPA authorized an Action Memorandum for a time-critical removal action (TCRA) to install a gate system at both entry points to prevent future dumping at the site, as well as remove and dispose of the 109 drums and contaminated soil. 

From June 23 to July 13, 2025, EPA completed the following:

  • Installed gates to limit access and deter future dumping along Martin Luther King Jr Blvd and at the northeast corner of the property.
  • Overpacked 103 drums and placed them in Conex boxes to await disposal.
  • Excavated soil six inches below surface level from the original dump sites.
  • Placed orange construction fencing around excavated areas while awaiting sampling results to confirm removal of impacted soil.

On August 14-15, 2025, EPA transported five roll-off bins of contaminated soil to an approved disposal facility.

On August 26-29, 2025, EPA transported the 103 drums to the approved disposal facility. EPA also backfilled the excavated areas with crushed rock and removed two of the three Conex boxes. 

On September 2, 2025, EPA removed the final Conex box marking the completion of all site activities.

 

Click here to view the StoryMap.